Who welded this element? Traceability of a steel structure years later
Published: 2026-11-27
The claim arrives two years later: a cracked weld, flaking coating. The questions are always the same — who, when, from what material, with which procedure, in what conditions. From binders the answer takes days, and sometimes there is none.
1. Questions asked with every claim
| Question | Where the answer usually is | Problem |
|---|---|---|
| Which heat is this element from? | certificates in a binder, supplier delivery note | delivery from several heats, substitute from stock, offcut from another project |
| Who welded it and when? | timesheet, the foreman’s memory | several welders, stand-ins, no date at the element |
| Did the welder hold a valid qualification at the time? | welder’s file | 6-monthly confirmation checked “for today”, not for the day of welding |
| Which WPS? | WPS register | no link between WPS, joint and element |
| Which coating system, what thickness? | project coating report | different systems for element groups of one structure |
| In what conditions was it painted? | a measurement notebook or nothing | measured once a day, not when that element was painted |
| Who assembled it in the shop? | timesheet | no link to a specific element and date |
EN 1090-2 requires traceability of constituent products — the scope depends on the execution class and specification. In practice the client and the insurer expect answers for a specific element, not for “the project in general”.
2. What is on the label
- project number and element position, piece counter (e.g. 012/070) and a unique QR code;
- execution class and edge preparation grade (EN ISO 8501-3);
- abrasive blast cleaning (Sa 2½), RAL colour;
- protection system and film thickness in µm, corrosivity category and durability (e.g. C4/H) — or hot-dip galvanizing, duplex, fire protection coating;
- with several protection groups in one structure — the data of the group the element belongs to.
3. What every scan records
| Stage | Record |
|---|---|
| Sawing, burning | date and time, who scanned, material group — and through it the heat and certificate |
| Assembly, welding | date and time, worker (fitter, welder) |
| Painting | date and time, who; the software supports sensors in the paint shop — temperature, humidity and dew point at the time of painting |
| Dispatch | date and time, who |
A skipped stage (e.g. a painting scan exists but the welding scan is missing) is visible immediately, not when a claim arrives.
4. Why paper loses here
A 22 t hall from our database has 88 shipping positions, 443 element pieces and 359 parts from 31 material groups. Each piece goes through 4–6 stages. That is several thousand events per project — with a date, a person and a material. Recorded by hand they are incomplete, and years later impossible to search.
How it works in the software
Labels are printed from the shipping list, and a scan with an ordinary phone records the stage, time and worker. Years later, scanning the sticker or typing the element number shows the history of stages, workers and dates — and in the project the material group certificates, the coating system and the documents. The software also supports temperature and humidity sensors in the paint shop, which add the conditions to painting scans.
This paper does not replace the standard. The text of the standard and the project specification are binding.