Price per kg of a steel structure: what it consists of and what most often slips out of the estimate
Published: 2026-11-27
The price per kg is more than a dozen components, each depending on something else: the cutting plan, the section weight, the coating system, the contract terms. Missing one is enough for a project to stop making money.
1. Components and what they depend on
| Component | Depends on | What slips most often |
|---|---|---|
| Steel | purchase weight from the cutting plan, current supplier prices | waste assumed “by eye”, prices months old |
| Scrap recovery | waste weight, scrap price | deducted although offcuts stay in stock |
| Production labour | hours per tonne by section weight (kg/m), parts per tonne | one h/t rate for light and heavy structures |
| Cost per hour | net wage → gross → employer cost | using the net wage instead of the employer cost |
| Corrosion protection | m² per tonne, system and film thickness, preparation (Sa 2½), galvanizing with transport | m² from tonnage without section weight, transport to the galvanizer |
| Testing | VT, NDT extent per Table 24 | NDT left out in EXC2 |
| Welding qualification | whether the WPS cover the thicknesses in the design | new WPQR discovered only after signing |
| Shop drawings | by the fabricator or by the client | “the design is there anyway” |
| Transport | tonnes per truck, elements over 13.5 m | oversize transport |
| Erection | in scope or not; crew, days, crane | unclear scope in the quote |
| Fixed company costs | monthly costs ÷ shop throughput in tonnes | not included, or counted twice in the overhead |
| Steel financing | cost of money × days to payment | steel paid months before the final invoice |
| Retention, bank guarantee | percentage, period, bank fee | cost of money frozen for years |
| Warranty reserve, penalties | contract terms | no reserve |
2. Example: net wage vs employer cost (Poland, 2026)
An employee on a contract of employment earns PLN 80/h net. That is about PLN 114/h gross and about PLN 138/h employer cost (employer social security 20.48%). An estimate at PLN 80/h understates labour by more than 40%. The ratio differs by country — the principle does not.
3. Components depend on each other
- Section weight → hours → cost. The same tonne made of light sections means many times more cutting and welding than of heavy ones.
- Cutting plan → steel → scrap → stock. Waste changes the steel price and what returns to stock.
- Lead time → financing. Lead time counts from complete shop drawings, not from signing — and steel is bought earlier.
- Thicknesses in the design → WPS → qualification cost. No WPS for one thickness means test pieces and testing before production starts.
- Dimensions → transport. One 14 m element turns a standard truck into oversize transport.
4. Before the quote goes out
One number goes into the quote PDF. Behind it are assumptions that must be stated to defend the price when the scope changes: basis of the quote (which lists and revision), erection scope, film thickness and its source, steel price validity, lead time counted from shop drawings, retention terms.
How it works in the software
The software calculates the price from company data: waste from the quote’s cutting plan, prices from recent orders, shop hours by section weight, employer cost, fixed costs per tonne of throughput and contract risks. It shows what is missing in the estimate before the quote goes out.
This paper does not replace the standard. The text of the standard and the project specification are binding.