Price per kg of a steel structure: what it consists of and what most often slips out of the estimate

Published: 2026-11-27

The price per kg is more than a dozen components, each depending on something else: the cutting plan, the section weight, the coating system, the contract terms. Missing one is enough for a project to stop making money.

1. Components and what they depend on

ComponentDepends onWhat slips most often
Steelpurchase weight from the cutting plan, current supplier priceswaste assumed “by eye”, prices months old
Scrap recoverywaste weight, scrap pricededucted although offcuts stay in stock
Production labourhours per tonne by section weight (kg/m), parts per tonneone h/t rate for light and heavy structures
Cost per hournet wage → gross → employer costusing the net wage instead of the employer cost
Corrosion protectionm² per tonne, system and film thickness, preparation (Sa 2½), galvanizing with transportm² from tonnage without section weight, transport to the galvanizer
TestingVT, NDT extent per Table 24NDT left out in EXC2
Welding qualificationwhether the WPS cover the thicknesses in the designnew WPQR discovered only after signing
Shop drawingsby the fabricator or by the client“the design is there anyway”
Transporttonnes per truck, elements over 13.5 moversize transport
Erectionin scope or not; crew, days, craneunclear scope in the quote
Fixed company costsmonthly costs ÷ shop throughput in tonnesnot included, or counted twice in the overhead
Steel financingcost of money × days to paymentsteel paid months before the final invoice
Retention, bank guaranteepercentage, period, bank feecost of money frozen for years
Warranty reserve, penaltiescontract termsno reserve

2. Example: net wage vs employer cost (Poland, 2026)

An employee on a contract of employment earns PLN 80/h net. That is about PLN 114/h gross and about PLN 138/h employer cost (employer social security 20.48%). An estimate at PLN 80/h understates labour by more than 40%. The ratio differs by country — the principle does not.

3. Components depend on each other

  • Section weight → hours → cost. The same tonne made of light sections means many times more cutting and welding than of heavy ones.
  • Cutting plan → steel → scrap → stock. Waste changes the steel price and what returns to stock.
  • Lead time → financing. Lead time counts from complete shop drawings, not from signing — and steel is bought earlier.
  • Thicknesses in the design → WPS → qualification cost. No WPS for one thickness means test pieces and testing before production starts.
  • Dimensions → transport. One 14 m element turns a standard truck into oversize transport.

4. Before the quote goes out

One number goes into the quote PDF. Behind it are assumptions that must be stated to defend the price when the scope changes: basis of the quote (which lists and revision), erection scope, film thickness and its source, steel price validity, lead time counted from shop drawings, retention terms.

How it works in the software

The software calculates the price from company data: waste from the quote’s cutting plan, prices from recent orders, shop hours by section weight, employer cost, fixed costs per tonne of throughput and contract risks. It shows what is missing in the estimate before the quote goes out.

This paper does not replace the standard. The text of the standard and the project specification are binding.

See the software on your own job

Send a list from one project — in 20 minutes we’ll show cutting plans, orders, documentation and the estimate.

Prefer to talk? Call us — in 15 minutes we’ll tell you whether the software fits your shop and where to start.
✉ ContactDemo