Painting a steel structure: film thickness, litres of paint and the conditions that decide on claims
Published: 2026-11-27
Corrosion protection is the only part of a structure the client judges with the naked eye for years. Whether it lasts is decided by numbers: thickness, volume solids, surface preparation and the conditions at the time of application.
1. Where the film thickness comes from — three sources, often contradictory
| Source | What it says | Watch out |
|---|---|---|
| EN ISO 12944-5 | example systems for corrosivity categories (C1–CX) and durability (L–VH) | examples, not a manufacturer guarantee |
| Manufacturer data sheet / system | thickness at which the manufacturer rates the system for the category and durability | may differ from the standard’s table |
| Design / national technical assessment | thickness required by the designer or by a national assessment of the product | takes precedence and must be in the quote |
The quote should state which thickness was assumed and where it comes from. 120 µm vs 160 µm is a third more paint — and a dispute at acceptance.
2. From thickness to litres
Theoretical spreading rate: volume solids [%] × 10 ÷ dry film thickness [µm] = m²/l.
| Data | Value |
|---|---|
| Area | 1,000 m² |
| Dry film thickness | 140 µm |
| Volume solids | 59% |
| Theoretical spreading rate | 59 × 10 ÷ 140 ≈ 4.2 m²/l |
| Paint without losses | ≈ 238 l |
Plus spraying losses — depending on the method (airless, conventional) and the shape of the elements — and thinner per the data sheet. Wet film thickness to check during application = dry film thickness ÷ volume solids as a fraction (140 ÷ 0.59 ≈ 237 µm), corrected for thinning.
3. Where the m² comes from — section weight
Painting area calculated “from tonnage” with one number is the most common estimating error. A tonne of light sections has several times more surface than a tonne of heavy ones. From material lists in our database: L50x5 about 50 m²/t, IPE200 about 36 m²/t, HEA200 about 28 m²/t, HEB300 about 15 m²/t.
4. Application conditions
- surface preparation per EN ISO 8501-1 (e.g. Sa 2½) and edges per EN ISO 8501-3 (P1–P3);
- substrate temperature at least 3 °C above the dew point;
- humidity and temperature within the range of the paint data sheet;
- overcoating intervals per the data sheet — depending on temperature.
A measurement once a day does not prove the conditions at the time a specific element was painted. With a coating claim this is the first question.
5. Where it gets complicated
- One structure, several protection groups — different systems, thicknesses and colours for different elements.
- Hot-dip galvanizing (EN ISO 1461) and duplex — transport to the galvanizer and back, different weight, different lead time.
- Dry film thickness measurements per EN ISO 19840 — how many points, which criteria, on which elements.
- A system change after the quote — different litres, different price, different labels, different documentation.
6. What goes into the documentation
Corrosion protection report: preparation grade, system and manufacturer, data sheet, paint batches, thickness measurements, application conditions — for each protection group.
How it works in the software
The software selects a manufacturer system for the corrosivity category and durability, shows the thickness per standard, national assessment and manufacturer, calculates m² from the lists and litres from the data sheets. QR labels carry the system and thickness of the group, a painting scan records the time, and sensors in the paint shop, which the software supports, add temperature, humidity and dew point.
This paper does not replace the standard. The text of the standard and the project specification are binding.