Lead time of a steel structure: why the promised date slips

Published: 2026-11-27

The date in a quote is a promise based on what the shop will do in a few weeks — together with other projects, holidays and the paint shop. Most often it is given from experience. Most often it also slips.

1. What the lead time depends on

FactorWhy it changes the date
Project queue in the shopa new project starts behind what is already in production — at every workstation separately
Bottleneckthe slowest workstation sets the date; in many shops it is the paint shop, not cutting
Section weighta tonne of light sections is many times more work than a tonne of heavy ones
Painting areathe paint shop is loaded by square metres, not tonnes
Crew and holidaysthe holiday of an experienced fitter changes assembly speed more than that of a helper
Shop drawingsthe date counts from complete drawings for the full scope, not from signing the contract
Steel deliveries and galvanizingmaterial, exact lengths from the mill, transport to the galvanizer and back
Shippingthe structure leaves in truckloads, not a tonne per day

2. Typical method errors

  • Average “days per tonne” from previous projects. Small projects with breaks inflate the average — for a 100 t building such an average can give a year of assembly.
  • Wrong painting area. The paint shop is loaded by square metres. In one case from our database, a wrong painting area of one project shifted the forecast for a new 10 t project by about 7 months (from January to August). After correcting the data — back to January.
  • The shop is “free” because nothing is planned. An empty week says nothing about shop capacity, only about the lack of orders.
  • Holidays in the calendar, but not in the plan. The plan assumes a full crew, and in August there is none.

3. Why it matters in the contract

Liquidated damages are charged for every day of delay. A date given “from experience” without the queue and holidays means either a risk of penalties or an inflated date that loses the tender. Add financing: steel bought early sits frozen until the invoice.

How it works in the software

The software calculates the date from the real pace of workstations in recent weeks, the project queue, section weight, painting area, crew and holidays entered ahead. Estimating gets the date for a new project before the quote goes out, and the schedule updates itself from QR scans.

This paper does not replace the standard. The text of the standard and the project specification are binding.

See the software on your own job

Send a list from one project — in 20 minutes we’ll show cutting plans, orders, documentation and the estimate.

Prefer to talk? Call us — in 15 minutes we’ll tell you whether the software fits your shop and where to start.
✉ ContactDemo