Sections worth tens of thousands lie in the yard, and the same profile is ordered for a new project. Not out of laziness — because nobody knows for sure what is there, how long it is, whether it is promised to another project and whether it has a certificate.

1. Scale

The stock of one fabricator in our database: 326 items, 758 pieces, 203 different sections. More than 100 pieces are offcuts under 2 m, about 330 are full lengths of 6 m and more. Almost every item has its yard location in the description — without it nobody finds the section.

2. Why stock material does not go back into production

CauseWhat happens
Spreadsheet ≠ yardoffcuts after cutting are not added, withdrawals are not deducted
Reservationsthe same section “taken” into cutting plans of two different projects
Not foundthe item is on record but not in the yard — the cutting plan must be recalculated
Different namesquare tube in stock, RHS in the design list — same size, but nobody matches it
No certificatea piece without an assigned certificate cannot go to a project with 3.1 documentation
Nobody plans with stockcutting planned only from commercial lengths — the stock keeps growing

3. Real examples (no names)

  • While cleaning up the offcut queue we found 406 recorded offcuts from cutting plans that had long been changed or deleted — “material” that never existed.
  • A short HEA160 part of 175 mm: instead of cutting a new bar, a 1.7 m piece from stock was enough.
  • A group removed from the design after the steel was ordered: 19 pieces ordered and paid for have to be booked into stock so they do not disappear.

4. Connections

Stock connects to the cutting plan (what we take), the order (what we do not buy), production (what was withdrawn and what is left after cutting), certificates (which heat) and other projects (what is already promised). The stock changes with every cut. A spreadsheet updated once a week is out of date after the first change on the shop floor.

How it works in the software

The cutting plan takes stock into account and reserves pieces for the project. The saw operator confirms withdrawals on a phone and books offcuts with their yard location, “not found” stops an outdated cutting plan, and for stock material the software picks the certificate from the company archive.

This paper does not replace the standard. The text of the standard and the project specification are binding.

See the software on your own job

Send a list from one project — in 20 minutes we’ll show cutting plans, orders, documentation and the estimate.

Prefer to talk? Call us — in 15 minutes we’ll tell you whether the software fits your shop and where to start.
✉ ContactDemo