Ordering steel for a project: why something is always missing or left over
Published: 2026-11-28
The steel order is where errors in lists and cutting plans turn into money: a shortage at the saw stops production, a surplus sits in the yard for years. And after the order is sent, the design keeps changing.
19 piecesordered and paid for a group that dropped out of the design after ordering
In short
- total metres from the list do not tell how many bars to buy
- one material group split between several suppliers
- revision after ordering: new parts without steel, steel without parts
material listcutting planstocksuppliers and pricesordersupplier certificates
1. What an order is made of
| Input | What it changes in the order |
|---|---|
| Material list | sections, grades, lengths and number of parts |
| Cutting plan | how many bars of which length — 6 m, 12 m or exact length from the mill |
| Stock | what we take from the yard instead of buying |
| Splicing | less steel, but extra welds and documentation |
| Suppliers and stockholders | available lengths and stock — one group split between several suppliers |
| Prices | price per kg depends on supplier and length |
| Certificates | every supplier must send certificates for its part |
2. Real examples (no names)
- An 88 t project: ordered from three suppliers plus stock, four list revisions during execution, ten material groups locked after ordering so the cutting plan could no longer change them.
- A group removed from the design after ordering: 19 pieces ordered and paid for that have to be booked into stock.
- Purchase surplus of sections over structure mass in orders from our database: from about 5% to over 50% — depending on the section and cutting plan.
3. Where shortages and surpluses arise
- Ordering from the list, not the cutting plan — total metres do not tell how many bars to buy.
- Revision after ordering — new parts without steel, steel for removed parts with no use.
- Supplier swaps lengths — no 12 m available, 6 m sent: the cutting plan no longer fits.
- Partial deliveries — a shortage shows up only at the saw.
- Stock “by eye” — the piece meant to come from the yard has already been used in another project.
How it works in the software
The order is created from the cutting plan and stock, split by supplier, length and price. After a revision the software shows what is missing from the order, and groups marked as ordered are locked against changes. Every supplier gets a link for certificates for its part.
This paper does not replace the standard. The text of the standard and the project specification are binding.