Splicing steel sections: when it pays off and what it entails
Published: 2026-11-27
A butt splice lets you cut a part from two pieces instead of a new bar. The steel saving is visible immediately; costs and obligations show up only in production and documentation.
1. The calculation: steel vs splice
HEA200 weighs about 42.3 kg/m. If a splice saves buying 2.3 m, that is about 97 kg of steel. On the other side is the cost of the splice: edge preparation, full penetration welding, testing, shop time and documentation. A splice pays off only when the steel saved is worth more than that cost — and this depends on the section, the steel price and your company’s rates, not on a rule of “always” or “never”.
2. What one splice entails
| Area | Requirement |
|---|---|
| Designer | approval of the splice and its position — outside the zone of maximum moments |
| WPS / WPQR | full penetration butt weld for both section thicknesses — e.g. HEA200: flange 10 mm, web 6.5 mm |
| Welder | EN ISO 9606-1 qualification covering butt welds, position and thickness |
| Testing | splice in tension = transverse butt weld in Table 24: in EXC2 10% at U ≥ 0.5; the project test plan may require more |
| Material | two pieces may come from two heats — one part, two certificates in the documentation |
| Production | two cutting items instead of one, marking of pieces, fit-up before welding |
| Documentation | spliced parts schedule: part, element, split, WPS, WPQR, signatures of welding coordinator and designer |
3. Where it gets complicated
- Profitability has to be calculated for each section and bar length separately — at 12 m a splice may pay off, with an exact mill length it may not.
- Allowing splicing changes the whole cutting plan of the section, and with it the order and the offcuts going to stock.
- A missing WPS for the web or flange thickness shows up only in the splice schedule — if that is prepared during production, it is too late.
- A list revision can remove a part whose splice was approved and add a new one that has no approval.
How it works in the software
The software compares cutting plans with and without splicing, using steel and splice costs from your rates, and splices only where it pays off. The spliced parts schedule with matching WPS and WPQR is created at the start of the project, and a missing WPS for a thickness is visible immediately.
This paper does not replace the standard. The text of the standard and the project specification are binding.