Scope changes and design revisions: how not to give money away in a variation

Published: 2026-11-27

A design rarely stays as it was in the quote. One 88 t project from our database had four list revisions during execution. Each changes mass, material, cutting and documentation — and for the variation it has to be calculated before the client forgets what was ordered.

1. What one revision changes

AreaQuestion
Masshow much was in the quote, how much is there today — added, removed and changed members separately
Materialis the steel for removed members already ordered or cut
Cutting planwhich groups to recalculate, which are locked because the material is already ordered
Productionwhat is already cut, welded, painted
QR labelswhich labels stay, which to cancel, which to reprint
Certificatesnew material groups without certificates, certificates of groups that no longer exist
Documentationreports and NDT extent for new members, WPS for new thicknesses
Lead timehow much extra work at each workstation

2. Where the fabricator loses

  • No reference point. Without the mass and assumptions recorded when the quote was accepted, it is hard to prove the scope changed.
  • Steel for removed members. Ordered and paid for, it does not reach the variation and ends up in stock.
  • Work already done. Members cut or welded before the revision — a cost that has to be shown.
  • Documentation added at the end. New members without certificates and reports discovered at handover.
  • The same part in two versions. Doubling after a list replacement inflates material and the order.

3. What should go into the variation

Mass in the quote and mass today broken down by change, material ordered for removed members, work done before the revision, impact on the date, additional testing and welding qualifications. Without these numbers a variation discussion is a negotiation “on trust”.

How it works in the software

When a quote is accepted, the software records its assumptions. The project card shows the mass in the quote and the mass today, scope changes ready for the variation and a reconciliation: quote assumptions vs real hours, steel and transport. A list revision recalculates the cutting plan and the order, and groups marked as ordered are locked against changes.

This paper does not replace the standard. The text of the standard and the project specification are binding.

See the software on your own job

Send a list from one project — in 20 minutes we’ll show cutting plans, orders, documentation and the estimate.

Prefer to talk? Call us — in 15 minutes we’ll tell you whether the software fits your shop and where to start.
✉ ContactDemo