Man-hours per tonne: why two similar projects differ more than threefold
Published: 2026-11-28
Labour is the largest price component after steel, and the quote usually carries one hours-per-tonne figure “from experience”. Time tracking data from one shop shows how much that figure can vary — and what a mistake costs.
- labour is the largest price component after steel
- 22 h/t in the quote vs 42 h/t from shop data = about PLN 300k
- without a reconciliation the same error goes into the next quote
1. Shop data
| Project (completed) | Mass | People on the project | Man-hours | h/t |
|---|---|---|---|---|
| A | 39 t | 17 | 748 | 19 |
| B | 24 t | 18 | 1,545 | 64 |
Same shop, similar crew, similar scale — more than three times the hours per tonne. Hours from daily time tracking booked to projects.
2. What hours per tonne depend on
| Factor | Why |
|---|---|
| Section weight | a tonne of light sections means many parts, cuts and welds; a tonne of heavy ones — a few |
| Parts per tonne | every part is cutting, holes, marking, tacking, welding, a label |
| Welds | fillet or full penetration, execution class, test extent |
| Type of structure | portal frames, platforms, railings, stairs — different work per tonne |
| Protection | painting counts in m², not tonnes; galvanizing needs different detailing |
| Crew | pace of an experienced fitter vs a helper |
3. The cost of a mistake
Example from our database: a quote for about 112 t assumed 22 h/t, while shop data for that section weight pointed to about 42 h/t. A difference of 20 h/t × 112 t is about 2,240 man-hours. At an employer cost of about PLN 138/h (example from Poland, 2026) that is about PLN 300k missing from the price — or, with the opposite error, a lost tender.
4. Why “from experience” is not enough
- You remember the last project, not the average over two years.
- Without hours booked to projects, nobody knows what a “successful” project really cost.
- Without a post-project reconciliation, the same error goes into the next quote.
How it works in the software
Employee hours booked to projects in time tracking give the shop’s real h/t by section weight. Estimating suggests hours for a new quote from this data, and after the project the reconciliation shows the quote assumptions next to the real hours.
This paper does not replace the standard. The text of the standard and the project specification are binding.