Man-hours per tonne: why two similar projects differ more than threefold

Published: 2026-11-28

Labour is the largest price component after steel, and the quote usually carries one hours-per-tonne figure “from experience”. Time tracking data from one shop shows how much that figure can vary — and what a mistake costs.

64 h/tin one completed project, 19 h/t in another — same shop, similar scale
In short
  • labour is the largest price component after steel
  • 22 h/t in the quote vs 42 h/t from shop data = about PLN 300k
  • without a reconciliation the same error goes into the next quote
project A (39 t)
19 h/t
project B (24 t)
64 h/t
112 t quote — assumed
22 h/t
112 t quote — shop data
42 h/t

1. Shop data

Project (completed)MassPeople on the projectMan-hoursh/t
A39 t1774819
B24 t181,54564

Same shop, similar crew, similar scale — more than three times the hours per tonne. Hours from daily time tracking booked to projects.

2. What hours per tonne depend on

FactorWhy
Section weighta tonne of light sections means many parts, cuts and welds; a tonne of heavy ones — a few
Parts per tonneevery part is cutting, holes, marking, tacking, welding, a label
Weldsfillet or full penetration, execution class, test extent
Type of structureportal frames, platforms, railings, stairs — different work per tonne
Protectionpainting counts in m², not tonnes; galvanizing needs different detailing
Crewpace of an experienced fitter vs a helper

3. The cost of a mistake

Example from our database: a quote for about 112 t assumed 22 h/t, while shop data for that section weight pointed to about 42 h/t. A difference of 20 h/t × 112 t is about 2,240 man-hours. At an employer cost of about PLN 138/h (example from Poland, 2026) that is about PLN 300k missing from the price — or, with the opposite error, a lost tender.

4. Why “from experience” is not enough

  • You remember the last project, not the average over two years.
  • Without hours booked to projects, nobody knows what a “successful” project really cost.
  • Without a post-project reconciliation, the same error goes into the next quote.

How it works in the software

Employee hours booked to projects in time tracking give the shop’s real h/t by section weight. Estimating suggests hours for a new quote from this data, and after the project the reconciliation shows the quote assumptions next to the real hours.

This paper does not replace the standard. The text of the standard and the project specification are binding.

See the software on your own job

Send a list from one project — in 20 minutes we’ll show cutting plans, orders, documentation and the estimate.

Prefer to talk? Call us — in 15 minutes we’ll tell you whether the software fits your shop and where to start.
✉ ContactDemo