Gantt chart in steel fabrication: how to read it and what it gives the shop

Published: 2026-11-28

A Gantt chart looks simple: bars on a timeline. But in a fabrication shop every bar is tonnes passing through several workstations shared by all projects at once. The chart is only as good as the data behind it — and only then answers the question every client asks: when?

2028 → 2027forecast for a 110 t project: from average “days per tonne” — 2028, from real workstation capacity — February 2027
In short
  • the bottleneck sets the date — look for the workstation with no gaps between bars
  • a bar that moved since last week always has a cause
  • the chart is only as good as the shop data
wk
13579
Project A
cutting
welding
painting
shipping
Project B
cutting
welding
painting
shipping
Project C
cutting
welding
painting
shipping
today

paint shop with no gaps = bottleneck · sample data

1. What is on the chart

ElementWhat it meansWhat to look at
Rowa project or its phaserow order = the shop’s priority queue
Bar in a rowproduction stage: cutting, welding and assembly, painting, shippingstart and end of each stage separately
Bar fillprogress — how many tonnes have passed the stageprogress behind the “today” line = delay
“Today” linethe current dateeverything to its left should be done
End of the last barforecast shipping datecompare with the contract date
Milestonesshop drawings, steel delivery, galvanizing, handovera stage will not start before its milestone

2. How to read it

  • Bottleneck first. Look for the workstation where project bars stand one behind another with no gaps. It sets the date for everyone — in many shops the paint shop, not cutting.
  • Then the shifts. A bar that moved since last week has a cause: design revision, missing steel, holidays, a project inserted higher in the queue.
  • Stages overlap. Welding starts before cutting ends — that is normal. Painting before welding ends less so, because the paint shop needs batches of members.
  • Shipping is truckloads. The structure leaves in batches after painting, not a tonne per day.

3. When the chart lies

CauseReal example (no names)
Pace from each project’s average “days per tonne”a 110 t project forecast to finish in 2028; calculated from real workstation capacity — February 2027
Wrong input dataan inflated painting area of one project shifted a new project’s forecast by about 7 months
A tonne is not a tonnea tonne of light sections is many times more work than heavy ones — a chart in tonnes without section weight misleads
“Full” crew all yearthe holiday of the fitter who does all the assembly extends assembly more than a helper’s
Chart drawn onceafter a week it no longer matches the shop, because nobody entered progress

4. What it gives the shop

  • A date for the quote — before the quote goes out, you see where the new project enters the queue and when it ships.
  • Decisions in advance — overtime, outsourced painting, queue changes, before liquidated damages become a fact.
  • Holidays — you see which week of a specific person’s holiday shifts which project.
  • Talking to the client — a concrete date and its reason instead of “we are doing our best”.
  • Shop floor — on a screen in the shop everyone sees the same queue.

How it works in the software

The schedule calculates itself from the real pace of workstations in recent weeks, section weight, painting area, crew and holidays entered ahead — including the pace of individual fitters. Progress comes from QR scans on the shop floor, and the same forecast goes into estimating a new project and onto the shop floor screen.

This paper does not replace the standard. The text of the standard and the project specification are binding.

See the software on your own job

Send a list from one project — in 20 minutes we’ll show cutting plans, orders, documentation and the estimate.

Prefer to talk? Call us — in 15 minutes we’ll tell you whether the software fits your shop and where to start.
✉ ContactDemo