Gantt chart in steel fabrication: how to read it and what it gives the shop
Published: 2026-11-28
A Gantt chart looks simple: bars on a timeline. But in a fabrication shop every bar is tonnes passing through several workstations shared by all projects at once. The chart is only as good as the data behind it — and only then answers the question every client asks: when?
- the bottleneck sets the date — look for the workstation with no gaps between bars
- a bar that moved since last week always has a cause
- the chart is only as good as the shop data
paint shop with no gaps = bottleneck · sample data
1. What is on the chart
| Element | What it means | What to look at |
|---|---|---|
| Row | a project or its phase | row order = the shop’s priority queue |
| Bar in a row | production stage: cutting, welding and assembly, painting, shipping | start and end of each stage separately |
| Bar fill | progress — how many tonnes have passed the stage | progress behind the “today” line = delay |
| “Today” line | the current date | everything to its left should be done |
| End of the last bar | forecast shipping date | compare with the contract date |
| Milestones | shop drawings, steel delivery, galvanizing, handover | a stage will not start before its milestone |
2. How to read it
- Bottleneck first. Look for the workstation where project bars stand one behind another with no gaps. It sets the date for everyone — in many shops the paint shop, not cutting.
- Then the shifts. A bar that moved since last week has a cause: design revision, missing steel, holidays, a project inserted higher in the queue.
- Stages overlap. Welding starts before cutting ends — that is normal. Painting before welding ends less so, because the paint shop needs batches of members.
- Shipping is truckloads. The structure leaves in batches after painting, not a tonne per day.
3. When the chart lies
| Cause | Real example (no names) |
|---|---|
| Pace from each project’s average “days per tonne” | a 110 t project forecast to finish in 2028; calculated from real workstation capacity — February 2027 |
| Wrong input data | an inflated painting area of one project shifted a new project’s forecast by about 7 months |
| A tonne is not a tonne | a tonne of light sections is many times more work than heavy ones — a chart in tonnes without section weight misleads |
| “Full” crew all year | the holiday of the fitter who does all the assembly extends assembly more than a helper’s |
| Chart drawn once | after a week it no longer matches the shop, because nobody entered progress |
4. What it gives the shop
- A date for the quote — before the quote goes out, you see where the new project enters the queue and when it ships.
- Decisions in advance — overtime, outsourced painting, queue changes, before liquidated damages become a fact.
- Holidays — you see which week of a specific person’s holiday shifts which project.
- Talking to the client — a concrete date and its reason instead of “we are doing our best”.
- Shop floor — on a screen in the shop everyone sees the same queue.
How it works in the software
The schedule calculates itself from the real pace of workstations in recent weeks, section weight, painting area, crew and holidays entered ahead — including the pace of individual fitters. Progress comes from QR scans on the shop floor, and the same forecast goes into estimating a new project and onto the shop floor screen.
This paper does not replace the standard. The text of the standard and the project specification are binding.