Declaration of performance and CE marking of a steel structure: what has to match
Published: 2026-11-27
A declaration of performance is one or two pages, but by signing it the manufacturer takes responsibility for the whole structure. Every value in it must follow from the rest of the documentation — which keeps changing until the last day of the project.
1. What is in the declaration and where it comes from
| Item in the DoP / CE | Source it must match |
|---|---|
| Manufacturer and FPC certificate number | notified body certificate — for the company that actually issues the declaration |
| Product and scope | project, phase, shipping list |
| Execution class (EXC) | design specification — may differ between member groups |
| Declaration method (M1, M2, M3a, M3b) | who designed — the manufacturer or the client |
| Materials, weldability, toughness | 3.1 certificates of material groups |
| Tolerances | dimensional reports |
| Durability | protection system: corrosivity category, coating thickness, galvanizing |
| Reaction to fire | product and coating |
2. Where the declaration starts contradicting the documentation
- Group of companies. The FPC certificate belongs to one company, the documentation is issued by another. In one case from our database, changing the issuing company meant correcting 102 documents in 12 projects in progress and re-signing 11 already signed.
- Coating thickness. 120 µm in the declaration, a different value on member labels, yet another in the paint manufacturer’s system.
- Project phases. One combined declaration or one per phase? Numbering must be continuous and unambiguous at handover.
- Several execution classes in one project. EXC2 and EXC3 members in one delivery — declaration and test extent per group.
- Signatory. The declaration is signed by a person authorised by the manufacturer — the authorisation must exist before it is used.
3. Why the end is the hardest part
The declaration is issued at the end, but its content depends on decisions made at the start: the executing company, execution class, protection system, steel suppliers. Every change along the way — revision, change of paint, substitute material — must reach the declaration, CE labels and the summaries in the as-built dossier.
How it works in the software
The declaration, CE label and as-built dossier are created from project data: the issuing company with its certificate, execution class and protection of each group, certificates and reports. A change in the project updates documents not yet signed, and for phases you can issue one combined declaration or separate ones.
This paper does not replace the standard. The text of the standard and the project specification are binding.