Cutting waste for steel sections: why 12% in a quote is a guess
Published: 2026-11-27
Quotes usually assume 12% waste. In the orders from our database the purchase surplus of sections over the structure weight ranged from 5% to over 50%. A fixed number sometimes inflates the price and sometimes eats the margin.
1. How much is really bought on top of the structure
| Project | Sections in the structure | Bought per cutting plan | Surplus |
|---|---|---|---|
| structure (quote) | 96.9 t | 103.8 t | 7.2% |
| structure (quote) | 30.0 t | 31.6 t | 5.2% |
| hall in production | 17.9 t | 21.6 t | 20.8% |
| hall in production | 15.3 t | 18.3 t | 19.6% |
| small projects / stages | 1.7–3.1 t | 2.1–4.0 t | 27–53% |
Surplus = purchase above the weight of sections in the structure: waste and offcuts returning to stock. Data from orders calculated from cutting plans, without client names.
At 100 t the difference between 7% and 12% is about 5 t of steel — in the quote price or in a lost tender. For a 2 t project, assuming 12% means a loss, because in reality 30–50% more is bought.
2. What drives waste
| Factor | What it changes |
|---|---|
| Part lengths vs stock lengths (6 m, 12 m, others at stockholders) | how much is left of each bar |
| Number of parts per section | few pieces = few combinations = more waste |
| Kerf and machine grip | how much fits on a bar in practice, not on paper |
| Splicing | less steel, but cost of the splice, WPS, testing and designer approval |
| Exact length from the mill | length matched to parts — on the mill’s terms and lead times |
| Offcut stock | whether matching pieces exist and are not reserved for another project |
| Grade and substitutes | whether grades can be combined and a substitute taken from stock |
3. Why “by eye” does not work
A section with 40 parts in several lengths can be arranged on bars in a very large number of ways, and the number grows explosively with every part. By hand you arrange the first reasonable variant, not the best one. And every section and grade is a separate cutting plan — the 22 t hall from our database had 31 such material groups.
4. What else depends on the cutting plan
- Steel price in the quote — you buy what the cutting plan says, not the weight from the list.
- Purchase order — number and length of bars for each supplier.
- Stock — which offcuts return to stock and where they are stored.
- Scrap — recovery from waste that cannot be used.
- Documentation — a part spliced from two bars may come from two heats, i.e. have two certificates.
Every list revision changes the cutting plan, and with it the order and the stock.
How it works in the software
The software calculates cutting plans straight from the quote lists: with stock lengths, offcut stock, splicing where it pays off and exact lengths from the mill. The quote gets the waste of this structure instead of an assumption, and the purchase order is created from the same cutting plan.
This paper does not replace the standard. The text of the standard and the project specification are binding.