As-built documentation in EXC2: 13 document types and hundreds of links between them

Published: 2026-11-27

The list of documents for EXC2 fits on one page. The difficulty lies elsewhere: a 22 t structure means about 125 pages in which every part, heat, welder and WPS must match — also after a design revision.

1. What goes to the client

#DocumentBasisMust match
1Declaration of Performance (DoP)Reg. (EU) 305/2011, EN 1090-1CE marking, project scope, FPC certificate
2CE markingEN 1090-1, Annex ZADoP number, notified body
3Inspection documents for materialsEN 10204; type per Table 1 of EN 1090-2section, grade and heat of every material group
4Certificates for welding consumablesEN 10204consumable stated in the WPS
5Certificates for fastenersEN 15048 / EN 14399class and coating from the design
6WPS + WPQREN ISO 15609-1, EN ISO 15614-1thicknesses, grades and joints in the project
7Welder qualificationsEN ISO 9606-1date of welding, process, position, thickness
8Visual testing report — 100% of weldsEN ISO 17637, EN ISO 5817 (C)list of elements, inspector qualification
9NDT reportsTable 24 of EN 1090-2; EN ISO 9712extent from the table or specification, tested joints
10Dimensional inspection reportEN 1090-2, Annex Belements and tolerances for the class
11Corrosion protection reportEN ISO 8501-1, EN ISO 12944, EN ISO 19840system from the design, film thicknesses, data sheet
12Welding recordsEN 1090-2, EN ISO 3834welder, WPS, element, date
13Erection (if in scope)EN 1090-2bolted connections, erection survey

Requirements on the fabricator side: FPC certificate per EN 1090-1 (system 2+) covering EXC2, welding coordinator per EN ISO 14731, welders per EN ISO 9606-1 with 6-monthly confirmation, qualified WPS — usually WPQR per EN ISO 15614-1.

2. Links that must be maintained

Example of a 22 t hall from our database: 88 shipping assemblies, 359 parts, 31 material groups, 26 heats, 44 WPS in the company register.

ChainScale in a 22 t projectWhat breaks consistency
part → material group → heat → certificate359 parts, 31 groups, 26 heatsdelivery from two heats, substitute section from stock, corrected certificate from the mill
certificate → supplier → deliveryseveral suppliers, partial deliveriescertificate issued to a stockholder, no delivery note linking the batch to the delivery
element → welder → date → qualification88 assemblies, several weldersexpired 6-monthly confirmation, stand-in on a shift
joint → WPS → qualification range44 WPS to reviewthickness out of range, different wire than in the WPS
welds → NDT extent → reportsper Table 24, per joint typedesign revision changing thicknesses or weld types
coating system → thickness → reportper protection groupdifferent systems for element groups, thickness from a national assessment different from the standard

Every list revision — a new element, a changed section, a different thickness — rearranges these chains. The documentation must describe the structure that left the shop, not the one from the first design issue.

3. Where it fails at acceptance

  • Certificate 2.2 instead of 3.1, or a certificate for a different section or grade than used.
  • No heat → element link — certificates exist, but nobody can say which element is made from which heat.
  • WPS does not cover the thickness from the design revision.
  • Welder without valid confirmation on the day of welding.
  • Wire on the certificate ≠ wire in the WPS (e.g. solid wire instead of flux-cored).
  • Certificate issued to a stockholder without a document linking the batch to the delivery.
  • NDT extent without justification per joint type.

4. Scale

A 22 t project: about 125 pages (76 pages of certificates, 49 pages of reports, declarations and welding log). An 88 t project: about 195 pages. Plus a table of contents and summaries, without which the client will not find the document for a specific element.

How it works in the software

The software keeps the links from the project list to dispatch and assembles the package into one PDF with a table of contents. Before the package goes out, it warns about every error from point 3 — also after a list revision.

This paper does not replace the standard. The text of the standard and the project specification are binding.

See the software on your own job

Send a list from one project — in 20 minutes we’ll show cutting plans, orders, documentation and the estimate.

Prefer to talk? Call us — in 15 minutes we’ll tell you whether the software fits your shop and where to start.
✉ ContactDemo